Planning site services around worker rotations
On a remote build, the headcount that matters isn't the number on the contract. It's how many people are on site today, and that changes every day of the week. Rotations drive almost every camp service, so they belong in the plan from the start.
Know your rotations
Different trades work different schedules. Crews on long stays often work 10 days on and 4 off, or two weeks on and one off. Once the structures are up and finishing trades arrive, many of them work five days and go home for two. Each pattern produces a different weekly curve.
Expect weekend swings
As more crews move to five-day weeks, weekends empty out. On the Caye Chapel build, a site serving 2,200 meals on a Wednesday can serve 1,200 on a Sunday. Food, staffing and ordering all have to follow that swing, or you pay for meals nobody eats.
Holidays don't mean zero
Over Christmas, New Year's and Easter, most of the workforce leaves, but security and the people who keep the site running stay. They still need three meals a day. Plan a scaled-down service for them, not a shutdown.
Laundry follows the rotation
A worker on a 10-day rotation needs laundry done once or twice per stay, not every day. That's why a laundry handling about 200 workers a day can serve a 2,000-worker rotation every ten days. Size it to the rotation, not to the total headcount.
Housing sets the ceiling
On an island, beds limit how many people can work at once. When the developer adds dormitories, headcount jumps, and food and camp services need notice to keep up. Share the housing plan with whoever runs the camp.
Count every day, bill accordingly
With numbers moving daily, a record of who was on site and who ate is the only fair way to bill. A QR scan at each meal gives a daily count by company, so food costs can be passed to each contractor based on what their crews actually used.
Read how we size service to the build and handle billing through one invoice, or tell us about your project.